• About
  • Advertise
  • Jobs
Monday, May 25, 2026
No Result
View All Result
KashmirPEN
  • Home
  • Latest NewsLive
  • State News
  • COVID-19
  • Kashmir
  • National
  • International
  • Education
  • Sports
  • Entertainment
  • Technology
  • Weekly
    • Perception
    • Perspective
    • Narrative
    • Concern
    • Nostalgia
    • Tribute
    • Viewpoint
    • Outlook
    • Opinion
    • Sufi Saints of Kashmir
    • Personality
    • Musing
    • Society
    • Editorial
    • Analysis
    • Culture
    • Cover Story
    • Book Review
    • Heritage
    • Art & Poetry
  • Home
  • Latest NewsLive
  • State News
  • COVID-19
  • Kashmir
  • National
  • International
  • Education
  • Sports
  • Entertainment
  • Technology
  • Weekly
    • Perception
    • Perspective
    • Narrative
    • Concern
    • Nostalgia
    • Tribute
    • Viewpoint
    • Outlook
    • Opinion
    • Sufi Saints of Kashmir
    • Personality
    • Musing
    • Society
    • Editorial
    • Analysis
    • Culture
    • Cover Story
    • Book Review
    • Heritage
    • Art & Poetry
KashmirPEN
No Result
View All Result
ADVERTISEMENT
Home Latest News

Div Com Kashmir reviews progress of National Highway Projects

Kashmir Pen by Kashmir Pen
9 months ago
in Latest News, State News
Reading Time: 2 mins read
Div Com Kashmir reviews progress of National Highway Projects
0
SHARES
8
VIEWS
Share on FacebookShare on Twitter

Divisional Commissioner (Div Com) Kashmir, Anshul Garg today convened a meeting to review the progress of National Highway Projects executed by agencies including NHAI, NHIDCL, BEACON, SAMPARK, & R&B.

The meeting was attended by Deputy Commissioners; officers of BEACON, SAMPARK & R&B; ED NHIDCL, representatives NHAI & MORTH; ACR Central, and other officers.

On the occasion, Div Com took stock of ongoing works, impediments and issues of NH1 Srinagar-Baramulla-Uri, NH 701 RD RKCTC, and rehabilitation issues of Jawahar Tunnel, NH 701A Narbal Surankote, NH501 Khanbal-Baltal, current status of MoRTH, Zojilla Tunnel Project, NH444 alignment issues, mining permission issues besides status of disbursement for land acquisition.

ADVERTISEMENT

He emphasized on adherence to timelines for obtaining approvals from the relevant authorities and commencement of works on the projects. He instructed DCs to address the issues related to various impediments like relocation of utilities and security installations falling in the alignment of projects.

Garg impressed on Director Geology & Mining for identification of Mining blocks and facilitating permissions for clay & boulders for construction of projects.

During the meeting, concerned officers of BRO, NHIDCL, NHAI & PWD shared the status of major projects executed by their departments.

Div Com enjoined executing agencies to actively pursue cases regarding permissions and other matters without wasting crucial time.

Meanwhile, he directed for re-appropriation of state funds from the districts which have received more funds under ring road projects to other districts especially Budgam & Baramulla.

Previous Post

Police provide frontline assistance to citizens in Kulgam

Next Post

Uneasy calm ends as flood threat eases in J&K

Kashmir Pen

Kashmir Pen

Next Post
Uneasy calm ends as flood threat eases in J&K

Uneasy calm ends as flood threat eases in J&K

Leave Comment
ADVERTISEMENT
Facebook Twitter Youtube RSS

©2020 KashmirPEN | Made with ❤️ by Uzair.XYZ

No Result
View All Result
  • Home
  • Latest News
  • State News
  • COVID-19
  • Kashmir
  • National
  • International
  • Education
  • Sports
  • Entertainment
  • Technology
  • Weekly
    • Perception
    • Perspective
    • Narrative
    • Concern
    • Nostalgia
    • Tribute
    • Viewpoint
    • Outlook
    • Opinion
    • Sufi Saints of Kashmir
    • Personality
    • Musing
    • Society
    • Editorial
    • Analysis
    • Culture
    • Cover Story
    • Book Review
    • Heritage
    • Art & Poetry

©2020 KashmirPEN | Made with ❤️ by Uzair.XYZ